Lochinvar KNIGHT 399 User Manual Page 18

  • Download
  • Add to my manuals
  • Print
  • Page
    / 76
  • Table of contents
  • BOOKMARKS
  • Rated. / 5. Based on customer reviews
Page view 17
Installation & Operation Manual
18
3 General venting
6. Priming and Cementing:
a. Handle fittings and pipes carefully to prevent
contamination of surfaces.
b. Apply a liberal even coat of primer to the fitting
socket.
c. Apply a liberal even coat of primer to the pipe end to
approximately 1/2" beyond the socket depth.
d. Apply a second primer coat to the fitting socket.
e. While primer is still wet, apply an even coat of
approved cement to the pipe equal to the depth of
the fitting socket.
f. While primer is still wet, apply an even coat of
approved cement to the fitting socket.
g. Apply a second coat of cement to the pipe.
h. While the cement is still wet, insert the pipe into the
fitting, if possible twist the pipe a 1/4 turn as you insert
it. NOTE: If voids are present, sufficient cement was
not applied and joint could be defective.
j. Wipe excess cement from the joint removing ring or
beads as it will needlessly soften the pipe.
Table 3A Vent Pipe, and Fittings
PVC/CPVC air intake/vent connections
1. Combustion Air Intake Connector (FIG.s 3-9 and 3-10) - Used to provide combustion air directly to the unit from
outdoors. A fitting is provided on the unit for final connection. Combustion air piping must be supported per guidelines
listed in the National Mechanical Code, Section 305, Table 305.4 or as local codes dictate.
2. Vent Connector (FIG.s 3-9 and 3-10) - Used to provide a passageway for conveying combustion gases to the outside.
Transition fittings are provided with the unit for final connection. Vent piping must be supported per the National Building
Code, Section 305, Table 305.4 or as local codes dictate.
6” COUPLING
(FIELD SUPPLIED)
6” CPVC
STARTER
PIECE
(FACTORY SUPPLIED)
VENT
AIR
THE 6” STAINLESS STEEL ADAPTER SUPPLIED
WITH THE BOILER MUST BE USED FOR VENT
CONNECTION TO PVC/CPVC. THE 6” CPVC
STARTER PIECE MUST BE USED FOR PVC ONLY.
Figure 3-10 Near Boiler PVC/CPVC Venting -
Models 700 - 800
VENT
AIR
4" CPVC PIPE SUPPLIED WITH
BOILER MUST BE USED FOR VENT CONNECTION
NOTE: CPVC VENT PIPE AND VENT FITTINGS MUST BE USED IN
CLOSET AND ALCOVE INSTALLATIONS.
*
* 4” CPVC STREET ELBOW
MAY BE SUBSTITUTED
Figure 3-9 Near Boiler PVC/CPVC Venting - Models 399 - 600
All vent pipe materials and fittings must comply with the following:
Item Material
Standards for installation in:
United States Canada
Vent pipe and fittings
PVC schedule 40 ANSI/ASTM D1785
CPVC and PVC venting must be ULC-
S636 Certified. IPEX is an approved
manufacturer in Canada supplying vent
material listed to ULC-S636.
PVC-DWV ANSI/ASTM D2665
CPVC schedule 40/80 ANSI/ASTM F441
AL29-4C UL1738 ULC-S636
Pipe cement/primer
PVC ANSI/ASTM D2564
IPEX System 636
Cements & Primers
CPVC ANSI/ASTM F493
NOTICE: DO NOT USE CELLULAR (FOAM) CORE PIPE
Approved Stainless Steel Vent Manufacturers
Make Model
ProTech Systems (Simpson Dura-Vent Co.) FasNSeal Vent / FasNSeal Flex* Vent
Z-Flex (Nova Flex Group) Z-Vent
Heat Fab (Selkirk Corporation) Saf-T Vent
*Use of FasNSeal Flex smooth inner wall vent is to be used in vertical or near vertical sections only, taking precaution to ensure
no sagging occurs of the vent system. Connect to the FasNSeal rigid vent using specially designed adapters and sealing method,
see manufacturer’s instructions.
Page view 17
1 2 ... 13 14 15 16 17 18 19 20 21 22 23 ... 75 76

Comments to this Manuals

No comments